Little River Interceptor Phase I

Newton County Water & Sewerage Authority

DATE OF SERVICES: May 2018 – April 2020

PROJECT STATUS: Complete

ROLE OF FIRM:

  • Jurisdictional Delineation and Permitting
  • Preliminary and Final Design

PROJECT TEAM:

  • Burke Murph – Project Manager
  • Matt Taylor – Quality Control
  • Claire Swaim – Senior Project Engineer
  • Barrett Neal – Assistant Project Manager
  • Michael Griffore – Senior Designer

CLIENT:  Newton County Water and Sewerage Authority

PROJECT DESCRIPTION:

The Newton County Water and Sewerage Authority (the Authority) requested engineering and design services for a new 18” PVC gravity sewer line connecting at the existing Little River Influent Pump Station and ending at GA Hwy 278.  GWES provided jurisdictional delineation services for approximately 22,000 LF from Little River IPS to Newton County line paralleling the Littler River following the preliminary corridor.  Based on the approximate location of the wetlands, streams and associated buffers within the project corridor, GWES provided the engineering design and permitting services for approximately 12,900 LF of 18” PVC gravity sewer line, along with associated manholes, in accordance with the Authority’s gravity sewer standards regarding pipe material, minimum cover depth, manhole spacing, markers, alignments, etc.